2- Steel Stud Framing (September 2005)
Steel framing of new walls began late summer 2005. Walls between classroom and control room sides are doubled, with a 1/2" gap between, allowing them to be soundproof. Studs are 2-1/2" wide 20 gauge steel.

» click on any photo to see the large view
thumbnail photo
Framing begins with installing wall studs (1/2' gap between)
thumbnail photo
Ceiling track installed.
thumbnail photo
Floor track being installed between classroom and studio.
thumbnail photo
Scoring stud with utility knife...
thumbnail photo
Studs beginning on camera 2 wall...
thumbnail photo
Metal snips used to cut sides of studs.
thumbnail photo
Camera 2 wall studs being installed.
thumbnail photo
Door 1 frame now in place.
thumbnail photo
Camera 2 wall almost fully framed.
thumbnail photo
Installing studs between studio and control room.
thumbnail photo
Framing window openings between studio and classroom.
thumbnail photo
Frame rough opening complete.
thumbnail photo
Special buck screws used for attaching metal to metal.
thumbnail photo
Corner berween cam1 and 2 walls, studio exit doorway leads out to fitness center.
thumbnail photo
Camera 1 wall completely framed (16 feet wide).
thumbnail photo
Camera 2 wall completely framed (12 feet wide).
thumbnail photo
Wall between studio and control room completely framed.
thumbnail photo
View from classroom side.
thumbnail photo
First sliding window installed in rough opening from previous window.
Tech TV Studio Construction 2005-2006 photos slideshow thumbnails
1- Demolition (Summer 2005) 13 click to start slide show click to see thumbnails
2- Steel Stud Framing (September 2005) 19 click to start slide show click to see thumbnails
3- Insulation and Drywall (October 2005) 20 click to start slide show click to see thumbnails
4- Painting (November 2005) 7 click to start slide show click to see thumbnails
5- Windows (December 2005) 14 click to start slide show click to see thumbnails
6- Countertops (January 2006) 26 click to start slide show click to see thumbnails
7-Finished TV Studio (December 2006) 26 click to start slide show click to see thumbnails
Former TV Studio Remodel Project 2004 photos slideshow thumbnails
TV Studio Pics from former studio design 14 click to start slide show click to see thumbnails
General Pictures photos slideshow thumbnails
Tech TV Studio Tour 18 click to start slide show click to see thumbnails